This was a 10 week programme which was completed on schedule with a contract
sum of £1 million.
The refurbishment of 162 rooms and 8 corridors programmed to run for 32 weeks and scheduled in 4 phases detailed below:
Phase 1 = 42 rooms + 2 Corridors
Phase 2 = 40 rooms + 2 Corridors
Phase 3 = 40 rooms + 2 Corridors
Phase 4 = 40 rooms + 2 Corridors
Contract sum of 1.8 million pounds
Redecoration of designated areas of the hotel, details listed below, and the work was carried out on a night shift programme to minimise the disruption to the hotel and guests.
Redecoration of Lounge/Bar Area
Reception
Restaurant Ceiling
Bedroom Corridors x 2
Bedroom Staircase
Gym
Meeting Rooms x 7
An 8 week contract, with a contract sum of £
65,000
Refurbishment programme of 3 corridors, 32 rooms including the provision of two disabled rooms. This is a 3 phase’s contract as listed below:
Phase 1 14 Rooms and a corridor to be completed in 4 weeks.
Phase 2 14 Rooms and a corridor to be completed in 4 weeks.
Phase 3 7 Rooms (which includes the conversion to disabled rooms) and a corridor
to be completed in 4 weeks.
Contract Sum of £192,000
Refurbishment of 49 bedrooms 7 corridors and 2 stairwells, in 6 phases as
detailed below:
Phase 1 = 6 bedrooms + Corridor 5 weeks
Phase 2 = 10 bedrooms + Corridor 6 weeks
Phase 3 = 5 bedrooms + Corridor 4 weeks
Phase 4 = 9 bedrooms + Corridor 5 weeks
Phase 5 = 9 bedrooms + Corridor 6 weeks
Phase 6 = 10 bedrooms + Corridor 6 weeks
This is a 32-week contract and a contract sum of £
470,000